Agenda Item
Meeting Date: 3/6/2019 - 4:00 PM
Category: Facilities
Type: Action
Subject: 21.1 Approve Change Order #27 for Central Valley Environmental Agreement #17-24-02 for the Tahoe Lake Elementary School Modernization & Addition Project
District Goals and Beliefs:
Belief 1 - Students are the focus of all decisions
Enclosure: Board Staff Report
TLE - CVE Agreement #17-24-02 Change Order #27
File Attachment:
Board Staff Report - TLE-CVE CO#27.pdf
TLE - CVE #17-24-02 CO#27.pdf
Summary: Change Order #27 to the original agreement for Central Valley Environmental captures the cost associated with lead and steel removal per Construction Change Directive #31. This change order also captures unforeseen asbestos removal at concrete footings per Request for Information #595.
Funding: $69,573 from Measure E Funds
Recommendation: Approve Change Order #27 for Central Valley Environmental Agreement #17-24-02 for the Tahoe Lake Elementary School Modernization & Addition project
Approvals:
Recommended By:
Signed By:
Jorge Rojas - Director of Facilities, Maintenance and Operations
Signed By:
Todd Rivera - Executive Director of Business Services
Signed By:
Robert Leri - Superintendent Chief Learning Officer
Vote Results:

Original Motion
Member Gaylan Larson Moved, Member Kirsten Livak seconded to approve the Original motion 'Approve Change Order #27 for Central Valley Environmental Agreement #17-24-02 for the Tahoe Lake Elementary School Modernization & Addition project'. Upon a Roll-Call Vote being taken, the vote was: Aye: 4 Nay: 0.
The motion Carried 4 - 0
   
Gaylan Larson     Yes
Kirsten Livak     Yes
Dianna Driller     Yes
Cristina Hennessey     Yes