Agenda Item
Meeting Date: 2/6/2019 - 4:30 PM
Category: Facilities
Type: Action
Subject: 21.1 Approve Change Order #8 for Lawson Mechanical Contractors Agreement #17-24-11 for the Tahoe Lake Elementary School Modernization & Addition Project
District Goals and Beliefs:
Belief 1 - Students are the focus of all decisions
Enclosure: Board Staff Report
TLE - Lawson #17-24-11 Change Order #8
File Attachment:
Board Staff Report - TLE-Lawson CO#8.pdf
TLE - Lawson #17-24-11 CO#8.pdf
Summary: Change Order #8 to the original agreement for Lawson Mechanical Contractors captures the cost for revising ductwork, louvers, and piping per Request for Information #240 and Architectural Supplement Instruction #18 for Tahoe Lake Elementary School.
Funding: $87,803 from Measure E Funds
Recommendation: Approve Change Order #8 for Lawson Mechanical Contractors Agreement #17-24-11 for the Tahoe Lake Elementary School Modernization & Addition project
Approvals:
Recommended By:
Signed By:
Jorge Rojas - Director of Facilities, Maintenance and Operations
Signed By:
Todd Rivera - Executive Director of Business Services
Signed By:
Robert Leri - Superintendent Chief Learning Officer
Vote Results:

Original Motion
Member Gaylan Larson Moved, Member Cristina Hennessey seconded to approve the Original motion 'Approve Change Order #8 for Lawson Mechanical Contractors Agreement #17-24-11 for the Tahoe Lake Elementary School Modernization & Addition project'. Upon a Roll-Call Vote being taken, the vote was: Aye: 4 Nay: 0.
The motion Carried 4 - 0
   
Gaylan Larson     Yes
Kim Szczurek     Yes
Dianna Driller     Yes
Cristina Hennessey     Yes